The first Concrete Slab was poured on December 15th in the front classroom wing.  The project experienced some rain delays this month, with approximately 4 days of rain.  Footings are 80% complete.  Masonry above finish floor is beginning.  DOT permit has been issued “finally”.  Be sure to review the following link for photographic updates, including drone flyovers.