With additional masonry crews now on site the concrete block masonry has accelerated.  The classroom wings masonry construction is 99% complete. Two of the classroom wings are roofed.  The HVAC duct system is scheduled for preliminary air pressure test this week (8, May 2017).  The fine arts balcony steel structure is in place ready for concrete pour.  The fine arts area masonry is 90% complete and is scheduled to be roofed by June 1, 2017.

Block fill primer paint is schedule to start in the classroom wings on or before June 1, 2017.

The project continues to track slightly ahead of schedule.  The construction manager continues to be diligent in staffing the jobsite.  Approximately 100 people are on site daily.  The owner architect and construction manager meet bi-weekly to review progress and address any issues that require attention.