Vidalia High School Update: March 21, 2018

The Vidalia High School Project is approaching completion more everyday.

The data infrastructure is underway with detail electrical work.

The heating and air conditioning system is operational for the entire facility.

The ceiling and ceiling cloud system is underway. The sound and light system in the fine arts area is underway.

All of the 100,000+ sqft of terrazzo flooring is installed and looks great.

Site work is moving forward to prepare for paving and landscaping.

Vidalia High School Update: November 21, 2017

The New Vidalia High School reaches another milestone toward completion. The interior and exterior finishes are underway.

The classroom wings have their terrazzo flooring installed and the walls are painted. The ceiling framing continues everyday. The exterior insulating stucco system is receiving the finishing color coat and detailing. The Fine Arts Auditorium and Gymnasium spaces get more impressive as they progress to completion.

 

The Board of Education members and administration toured the facility on Tuesday and were happy to see and hear that the project is ahead of schedule and remains on budget.

 

Vidalia High School Update: October 16, 2017

The New Vidalia High School continues to make progress toward the August 2018 opening.

The terrazzo flooring is underway and painting is progressing according to schedule.

 The large rooftop HVAC units are installed and prepping for startup.

The gymnasium is taking shape. The gym roof is scheduled to be complete this month.

The energy-efficient insulated glass continues installation. Most windows are complete in the classroom wings.

The Administration and teachers are excited to tour the facility and actually see their classrooms take shape.

 

Vidalia High School Update: July 24, 2017

Vidalia High School Update: July 24, 2017

[dt_gap height=”10″ /]

Update

The window installation is almost complete in the first classroom wing. The air conditioning duct system continues to make progress throughout the building.

The first prime coat of pain is nearing completion in the classroom wings. The HVAC equipment is expected to arrive in August so the building can begin to be climatized.

[dt_gap height=”10″ /]

The exterior brick masonry is making good progress.

[dt_gap height=”10″ /]

The project remains on schedule.

Check out the drone footage from TQ Constructors, Inc.