Pierce County High School Update: August 21, 2017

Pierce County High School Update: August 21, 2017

 

The site work is well underway. The 2017/2018 school year has begun and the temporary traffic measures are in place.

Security fencing is in place. School functions and construction activities are running simultaneously .

Utility relocation for the new road work is on schedule.

All site work tests indicate proper compaction and acceptable soil types.

At present the site contractor is moving and installing 3000 to 4000 yards of structural fill per day.

The project remains on schedule at this time.

 

Vidalia High School Update: July 24, 2017

Vidalia High School Update: July 24, 2017

[dt_gap height=”10″ /]

Update

The window installation is almost complete in the first classroom wing. The air conditioning duct system continues to make progress throughout the building.

The first prime coat of pain is nearing completion in the classroom wings. The HVAC equipment is expected to arrive in August so the building can begin to be climatized.

[dt_gap height=”10″ /]

The exterior brick masonry is making good progress.

[dt_gap height=”10″ /]

The project remains on schedule.

Check out the drone footage from TQ Constructors, Inc.

Pierce County High School Update: July 24, 2017

Pierce County High School Update: July 24, 2017

The site development package has been bid and awarded.

Five site contractors submitted bids. Hiers & Co was the low responsive bidder and after review of the bidder’s qualifications the contract was awarded to Hiers & Co from Baxley, GA.

Actual work on site has begun and is expected to move forward as weather permits.

Temporary road work is nearing completion in preparation for school opening.