The New Vidalia High School continues to make progress toward the August 2018 opening.

The terrazzo flooring is underway and painting is progressing according to schedule.

 The large rooftop HVAC units are installed and prepping for startup.

The gymnasium is taking shape. The gym roof is scheduled to be complete this month.

The energy-efficient insulated glass continues installation. Most windows are complete in the classroom wings.

The Administration and teachers are excited to tour the facility and actually see their classrooms take shape.