The fine arts auditorium shall be dried-in this week and the balcony is poured. The space is truly impressive.

The school maintenance staff started bi-weekly tours with the mechanical and electrical sub-contractors. These tours are part of the inclusive design/construction process SP Design promotes to help future operations of the facility.

Brick masonry has begun on the classroom wings. The foam insulation/vapor barrier system is installed on 2 classroom wings. The insulation systems used on the building envelope will help reduce energy use for the life of the building.

The gym structure is 95% complete and masonry is 60% complete.

A full engineering review and testing of the structural connections shall be completed before June 30th.

Review the embedded drone flyover for a photo update.