Week of April 4-10

  • On site review of the existing “Oxford” building has been done again in preparation for the demolition bid package.
  • TQ Constructors continues to discuss and budget items such as asbestos removal, removal of stored material, and building occupancy.
  • Demo package drawings continue and will be available to TQ on April 2016.┬áDesign Development drawings continue and shall be completed late April 2016.
  • Timeline has been updated and prepared for presentation to the Board of Education.
  • SP Design and TQ continue to discuss budget, building systems, schedule, and building details.
  • Initial HVAC equipment selection has been made and is under budget review.