Vidalia High School Update: July 24, 2017

Update The window installation is almost complete in the first classroom wing. The air conditioning duct system continues to make progress throughout the building. The first prime coat of pain is nearing completion in the classroom wings. The HVAC equipment is expected to arrive in August so the building can begin to be climatized. The…

Construction Update: Vidalia High School June 1, 2017

The fine arts auditorium shall be dried-in this week and the balcony is poured. The space is truly impressive. The school maintenance staff started bi-weekly tours with the mechanical and electrical sub-contractors. These tours are part of the inclusive design/construction process SP Design promotes to help future operations of the facility. Brick masonry has begun…

Construction Update: Vidalia High School May 9, 2017

With additional masonry crews now on site the concrete block masonry has accelerated.  The classroom wings masonry construction is 99% complete. Two of the classroom wings are roofed.  The HVAC duct system is scheduled for preliminary air pressure test this week (8, May 2017).  The fine arts balcony steel structure is in place ready for…

Construction Update: Vidalia High School December 30, 2016

The first Concrete Slab was poured on December 15th in the front classroom wing.  The project experienced some rain delays this month, with approximately 4 days of rain.  Footings are 80% complete.  Masonry above finish floor is beginning.  DOT permit has been issued “finally”.  Be sure to review the following link for photographic updates, including…