SUMMARY

This project consisted of four stages: existing building abatement, demolition of an existing high school structure, a site preparation effort and finally a building package. The building itself is based upon a site adapted prototype previously developed for the County. The color scheme and building orientation were tailored to conform to the site and the historical needs of the community. All packages were delivered using the design/bid/build delivery system.

Cost:

$10,442,500

Completion Date:

November 2007

Delivery Method:

Design/Bid/Build

Square Footage:

110,084 sq.ft