Vidalia High School Update
Mike Parker, Partner at SP Design Group, and Dr. Garret Wilcox, Superintendent of Vidalia City Schools discuss the new high school building program with Vidalia High school.
Mike Parker, Partner at SP Design Group, and Dr. Garret Wilcox, Superintendent of Vidalia City Schools discuss the new high school building program with Vidalia High school.
Brick masonry continues around the classroom wings. However the rainy weather conditions continue to impact schedule this week. The fine arts auditorium is taking shape now that all walls are in place and the structure and roof is in place. The line of sight from ALL seat locations in the auditorium can be experienced now…
The fine arts auditorium shall be dried-in this week and the balcony is poured. The space is truly impressive. The school maintenance staff started bi-weekly tours with the mechanical and electrical sub-contractors. These tours are part of the inclusive design/construction process SP Design promotes to help future operations of the facility. Brick masonry has begun…
With additional masonry crews now on site the concrete block masonry has accelerated. The classroom wings masonry construction is 99% complete. Two of the classroom wings are roofed. The HVAC duct system is scheduled for preliminary air pressure test this week (8, May 2017). The fine arts balcony steel structure is in place ready for…
It is an exciting time for Pierce County students and staff as the design for the new Pierce county high school progresses. The Board of Education was updated on the project Thursday, April 13th. Dara Bennett ,high school principal, helped explain the programming process and the inclusion of students and teachers in the programming/planning process.…
The front classroom wing is the first area to be roofed. The rear classroom wing is scheduled to be roofed next. 95% of all concrete slabs are complete. The concrete quality and installation remains very good. The brick has been selected and ordered for the entire job. All structural steel is on site and approximately…
Construction continues to progress on schedule for the new Vidalia High School. Approximately 80% of floor slabs are installed . The masonry walls are making good progress. The first bar joist was installed March 2. 2017. Site work is 85% complete. A new “small” concrete finisher shown in the photos left his mark on the…
The first Concrete Slab was poured on December 15th in the front classroom wing. The project experienced some rain delays this month, with approximately 4 days of rain. Footings are 80% complete. Masonry above finish floor is beginning. DOT permit has been issued “finally”. Be sure to review the following link for photographic updates, including…
Construction is in full swing now: The site work and utility construction continue at a good pace The building construction is making good progress with 60% of footing in place and foundation walls also at 60% complete As shown in the photo electrical and plumbing installation below slab is also in progress. The compaction test…